TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures
This document provides the process details for installation of the Single Turbine Subsystem (STS) device from the assembly laydown location to the deployed location in Eastport, ME. These procedures will be conducted not only during initial deployment, but also during maintenance events. These operational plans are for installation, deployment, retrieval and removal of the TidGen STS.
Citation Formats
TY - DATA
AB - This document provides the process details for installation of the Single Turbine Subsystem (STS) device from the assembly laydown location to the deployed location in Eastport, ME. These procedures will be conducted not only during initial deployment, but also during maintenance events. These operational plans are for installation, deployment, retrieval and removal of the TidGen STS.
AU - Martin, Taylor
DB - Marine and Hydrokinetic Data Repository
DP - Open EI | National Renewable Energy Laboratory
DO -
KW - MHK
KW - Marine
KW - Hydrokinetic
KW - energy
KW - power
KW - TidGen
KW - Single Turbine System
KW - STS
KW - TD80
KW - Advanced TidGen
KW - work plan
KW - tidal
KW - ORPC
KW - operational plans
KW - installation
KW - deployment
KW - retrieval
KW - removal
LA - English
DA - 2023/02/20
PY - 2023
PB - Ocean Renewable Power Company
T1 - TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures
UR - https://mhkdr.openei.org/submissions/541
ER -
Martin, Taylor. TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures. Ocean Renewable Power Company, 20 February, 2023, Marine and Hydrokinetic Data Repository. https://mhkdr.openei.org/submissions/541.
Martin, T. (2023). TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures. [Data set]. Marine and Hydrokinetic Data Repository. Ocean Renewable Power Company. https://mhkdr.openei.org/submissions/541
Martin, Taylor. TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures. Ocean Renewable Power Company, February, 20, 2023. Distributed by Marine and Hydrokinetic Data Repository. https://mhkdr.openei.org/submissions/541
@misc{MHKDR_Dataset_541,
title = {TidGen: Single Turbine Subsystem (STS) Device Installation, Deployment, Retrieval, and Removal Procedures},
author = {Martin, Taylor},
abstractNote = {This document provides the process details for installation of the Single Turbine Subsystem (STS) device from the assembly laydown location to the deployed location in Eastport, ME. These procedures will be conducted not only during initial deployment, but also during maintenance events. These operational plans are for installation, deployment, retrieval and removal of the TidGen STS.},
url = {https://mhkdr.openei.org/submissions/541},
year = {2023},
howpublished = {Marine and Hydrokinetic Data Repository, Ocean Renewable Power Company, https://mhkdr.openei.org/submissions/541},
note = {Accessed: 2025-05-06}
}
Details
Data from Feb 20, 2023
Last updated May 21, 2024
Submitted Feb 27, 2024
Organization
Ocean Renewable Power Company
Contact
Jarlath McEntee
207.772.7707
Authors
Keywords
MHK, Marine, Hydrokinetic, energy, power, TidGen, Single Turbine System, STS, TD80, Advanced TidGen, work plan, tidal, ORPC, operational plans, installation, deployment, retrieval, removalDOE Project Details
Project Name Advanced TidGen Power System
Project Lead Yana Shininger
Project Number EE0007820